D.H.W. programme 

Select the days that correspond with the heating phase. 
1= Monday, ... 7 = Sunday/8 = hot-water service programme

Start of phase 1: heating with fixed modality

End phase 1: heating with reduced modality

Start phase 2: heating with fixed modality

End phase 2: heating with reduced modality

Start phase 3: heating with fixed modality

End phase 3: heating with reduced modality

Copying of the daily programme

By pressing this key it is possible to repeat the current heating programme
for the 

next day

.

By pressing this key it is possible to repeat the current heating programme
for the 

previous day

.

As a confirmation the following day is displayed.

4

5

6

7

8

9

10

1 1

With the Logica Remote Control it is possible to manage the temperature of D.H.W. tank on
two  levels  (a  comfort  level  and  one  at  reduced  temperature)  in  accordance  with  the  pro-
gramme chosen with parameter 62 (load domestic hot water). To have access to the para-
meter press the 

and

keys for at least 5 seconds and then go along the entered lines

with the 

key until parameter 62 is reached. At this point four different programmes may

be selected with 

o

keys, with the following characteristics:

0

= 24 hours/ day - Hot water is always available at the temperature set with user parame-

ter n°3.

1

= standard - Hot water according to the daily heating programme. 

In the comfort areas of heating the temperature of the D.H.W. tank is regulated to the
value set with user parameter n° 3. 
In the reduced areas of heating the temperature of the D.H.W. tank is regulated to the
value set with parameter n° 61 of the service level.

2

= service disconnected

3

= second daily programme (8) - Every day of the week the temperature of the hot water is set

according to programme 8. In this case there is a single programming for all the days of the
week and three time zones are available. In the time spans set the temperature of the D.H.W.
tank  is regulated according to that set in parameter n°3. In the remaining hours the D.H.W.
tank is controlled to the temperature set with parameter n° 61 the of service level.

Start phase 1: preparation of the D.H.W. tank to the comfort temperature

End phase 1: Temperature of D.H.W. tank maintained at the reduced value

Start phase 2: Preparation of D.H.W. tank to the comfort temperature

End phase 2:  Temperature of D.H.W. tank maintained at the reduced value 

Start phase 3: preparation of D.H.W. tank to the comfort temperature

End phase 3: Temperature of D.H.W. tank maintained at the reduced value

5

6

7

8

9

10

Heating programme

With the heating programme it is possible to set the switching times of the temperature for a
period  of  a  week.  The  weekly  programme  consists  of  7  daily  programmes.  One  daily  pro-
gramme allows 3 phases of heating. Each phase is defined by a ignition time and a finishing
time. The n° 8 daily programme is for the domestic hotwater service. If a period is not required,
the same ignition and finishing time may be entered.

Summary of Contents for benchmark Planet Super 4 W. M.

Page 1: ...Planet Super 4 W M User Instructions GB PLEASE LEAVE THIS INSTRUCTION WITH THE USER ...

Page 2: ......

Page 3: ...knob The set temperature is displayed on the scale of the red leds from 40 80 C Regulation of the C H temperature is carried out by acting on the heating knob The set temperature is shown on the scale of the red leds from 40 80 C To guarantee an always optimal output from the generator it is advised not to go below a minimum operating tempera ture of 50 C TURNING OFF BOILER fig 1 To turn the boile...

Page 4: ...ing open the filling cock until the green led 1 bar lights up Once filled close the filling tap If all the leds are off call the authorised technical staff Safety stat interception fig 5 If the safety stat intercedes the red led 35 C intermittently lights up To start the boiler again turn the selector knob in the position and then release immedi ately returning it to the winter or summer function ...

Page 5: ...lacing the selector on the or posi tion obviously without consequent con trol of the room temperature The functioning instructions are inside the lid fig 8 Every setting or modifica tion is displayed and confirmed on the display fig 9 LOGICA REMOTE CONTROL 1 6 7 8 4 5 3 2 KEY 1 Display 2 Info key 3 Operating mode key automatic functioning 4 Operating mode key manual functioning 5 Operating mode ke...

Page 6: ...the follow ing list of items one after the other are dis played The thermosensor continues to func tion independently of the display Day hour room temperature External temperature D H W temperature This data appear only if the relative sensor is connected or if they are transmitted by the regulator of the boiler Info key reference key grey colour The operating mode desired is selected by pressing ...

Page 7: ...r at reduced level To have access to the reduced D H W temperature parameter press the and keys at the same time for at least 5 seconds and then go along the entered lines with the key until parameter 61 is reached Regulate the value with and Before proceeding with the adjustment in the temperature on the Logica controller the ther mostatic valves which may be present have to be regulated to the d...

Page 8: ...mperature of the D H W tank is regulated to the value set with user parameter n 3 In the reduced areas of heating the temperature of the D H W tank is regulated to the value set with parameter n 61 of the service level 2 service disconnected 3 second daily programme 8 Every day of the week the temperature of the hot water is set according to programme 8 In this case there is a single programming f...

Page 9: ...period 1 10 18 Vacation function To enter the number of days of absence In the display the vacation symbol will be shown on the left the day of activa tion 1 Monday 7 Sunday and on the right the number of vacation days 18 During the vacation the regulator will be on the availability mode When the set days have elapsed the regulator will go on to the automatic function NOTE The vacation period may ...

Page 10: ...ure Restore functioning by opening the filling cock of the boiler fig 4 System overpressure Call the authorised technical staff for assistance Safety stat interception Call the authorised technical staff for assistance Air pressure switch interception Call the authorised technical staff for assistance Failure of the modulating coil Call the authorised technical staff for assistance Communication f...

Page 11: ......

Page 12: ...Cod 6274223A Documentation Dpt Sime Ltd Unit D2 Enterprise Way Bradford Road Idle Bradford BD10 8EW Tel 0870 9911114 Fax 0870 9911115 www sime ltd uk e mail enquiries sime ltd uk ...

Reviews: