5 RACK MOUNT INSTALLATION
PROCEDURE
The SDB680 Base Station is designed to be fitted in a standard 403 mm
(19”) rack. This procedure should be followed when installing all new
SDB680 Base Stations into a 19” racking system.
5.1. TOOLS, TEST EQUIPMENT AND MATERIALS REQUIRED
The following Tools, Test Equipment and Materials will be required to perform this
procedure:
Pozidriv Screwdriver
4 x M6 x 12 mm Pozidriv Retaining Bolts
4 x M6 x 16 mm Pozidriv Retaining Bolts
8 x M6 Nuts and Plain Washers
M6 Cage Nuts
Anritsu/Wiltron S331A Test Set
Earth Bonding Test Set
5.2. RACK PREPARATION
Note.
Rack runner fittings differ between the various rack manufacturers. If the procedure
described below does not apply to the type of rack being used, the procedure should
be modified to suit.
1. Ensure that the rack chosen for installation is firmly bolted together and is
securely anchored to the floor or wall to prevent overbalancing.
2. In the rack, plan out the locations of equipment before commencing
installation.
3. Unpack all the equipment and retain the packaging.
Notes:
(i). Each SDB680 requires 2U height of rack space.
(ii). Unused space should be blanked off to prevent uncontrolled circulation of air.
(iii). If used, the associated PSU TRAY requires either 1U or 2U height of rack space
and is designed to locate adjacent to the base station.