V. MAINTENANCE
ATTENTION !!!
There are no parts inside the UPS or battery group that needs service or maintenance work that
should be done by user. Therefore DO NOT OPEN THE COVER OF UPS. Never touch on any terminal of battery
group. There is risk of electric shock inside the UPS even when it is completely turned off (because of energy
storage components). Therefore unauthorized openning of the UPS cabinet for repairment, maintenance etc. is not
recommended and forbidden. Otherwise serious injuries may happen.
5.1 Scheduled Maintenance
Some parts and components used inside UPS requires periodic maintenance by service personnel. Besides,
some power equipment inside the UPS need good air circulation for cooling functions. In this case, the UPS
should be cleaned against dust periodically. Cooling fans are mechanical and moving parts and they should be
checked periodically for this reason. Also the batteries should be checked periodically that if they are in good
condition or not.
LION Series UPS informs the user about these procedures when the maintenance time is up with its 3
independent hour counter as warnings:
FAN MAINTENANCE counter
BATTERY MAINTENANCE counter
GENERAL MAINTENANCE counter
This type of protective maintenance prevents small problems turning up to big failures.
LION Series UPS has been designed to require very low user maintenance work. User should only make
below maintenance procedure for long years of trouble-free operation.
5.2 Daily Checks
Observe the UPS daily and check the following:
Examine the operator control panel (front panel). Ensure that all LED indicators and parameter measurements are
normal and there is no warning or alarm messages on LCD display.
Examine that there is any sign of overheating the UPS or not.
Check the rotation of cooling fans visually.
Check if there is a remarkable change in the sound of UPS or not.
Check if air inlets of the cabinet cooling system are not congested with dust or any other foreign object. Clean
them with a vacuum cleaner if any present.
Take care not to leave any object on the UPS cabinet.
5.3 Weekly Checks
1. Examine the front panel and record the results.
2. Measure (from Measurements Menu) each of three phase voltages and record the values.
3. Measure (from Measurements Menu) UPS output current values and record the values.
4. Perform a Manual Battery Test (from Commands Menu) and check the status oft he batteries.
5. Cabinet covers may be cleaned with a soft damped (not wet) cloth.