1.1
MOBILISATION
The unit is equipped with fork lift pockets to mobilize this mixing unit. The weight of the unit is 1540 kg.
Prior to lifting the mixing unit a few checks must be made:
1.
Check if all stored articles on the mixing unit are securely tied down
2.
Take the ignition key out of the control panel
3.
Make sure the mixing tank, pump and piping is drained and cleaned
4.
Open all valves
NEVER:
1.
Stand or walk underneath the load
2.
Use certified lifting equipment
1.2
PLACING THE MIXING UNIT ON SITE
Before you place your mixing unit on location, make the following preparations:
1.
Place a sheet of 4x4 meters of oil resistant plastic foil on the location of the unit
2.
Place 3 drag line boards each at least 3 meter long horizontally, well supported by solid soil, on top of the plastic
foil
3.
If you decide not to use the plastic foil: always use drag line boards or something similar placed horizontally to
give the mixing unit its full support and to create a non-slippery working floor
The unit has the following connections:
1.
Water
:
2’’ id BSP thread
2.
Mud discharge :
3’’ victaulic
ring
The installed power is:
2L41c Hatz diesel stage V engine