Installation Instructions
Pump P 215
810-55192-1
Page 33 / 45
Rev. 012
2018/11/30
9.
Standard operation
9.1. Daily start-up
Below find the activities to be carried out in case of standard operation.
9.2. Inspections
With regard to “Inspections prior to initial commissioning”, the operator has to
define suitable inspection intervals depending on the actual operating conditions.
9.3. Filling the reservoir during operation
Fill the reservoir as described in Chapter “Installation and commissioning”
.
9.4. Cleaning
For cleaning, required protective clothes, cleaning agents and devices, observe
valid operation guidelines provided by the operator
.
DANGER
Danger to life
Risk of fire and explosion when using inflammable cleaning agents.
Do not use steam or high-pressure cleaners. Electrical components
may be damaged.
Do not touch cables or electrical components with wet or damp
hands.
Cleaning work on energized components may be carried out by
electrical specialists only.
Wear personal protective equipment.
Exterior cleaning
•
Thorough cleaning of all surfaces.
•
Mark and secure wet areas.
Interior cleaning
•
Normally, interior cleaning is not required.
ATTENTION
Possible damage to the machine
When using solvents for cleaning purposes, ensure their compatibility with plastic
parts and lacquers. Do not use polar organic solvents like e. g. alcohol, methanol
or acetone.
Summary of Contents for Lincoln 215-M049
Page 1: ...Installation Instructions Pump P 215 810 55192 1 Page 1 45 Rev 012 2018 11 30 P 215...
Page 23: ...Installation Instructions Pump P 215 810 55192 1 Page 23 45 Rev 012 2018 11 30...
Page 43: ...Installation Instructions Pump P 215 810 55192 1 Page 43 45 Rev 012 2018 11 30 M100 M049 100XY...