2. SET-UP CHECKLIST FORM:
Before setting up and using the working platform, the following checklist should be followed to ensure
that all requirements are met.
SAFETY EQUIPMENT
1.
Persons (users) trained in equipment use
2.
Instruction sheet given to users for safety equipment use
3.
Minimum of 2 persons to use
4.
Equipment in serviceable condition
5.
Equipment all present
6.
Relevant persons notified that works to be carried out inside the hold
SUSPENSION SYSTEM
1. Set-up done by qualified worker: Name : ............................ Id nr.: ...................
2. Equipment in correct position
3. Power supply cables in good condition, insulation OK.
4. Steel wire ropes in good condition.
5. Steel wire ropes diameter matches with equipment used. (9 mm).
6. Power lead plugged in, hung from rig and safely lowered.
7. Steel wire ropes connected correctly; shackles moused.
8. Steel wire ropes safely rigged to platform wire winders (optional)
9. All bolts in place and tightened
10. Additional securing arrangements for the Aluminum bracket in place.
11. General suspension equipment condition OK
12. Clamp plates safely connected to base channels
WORKING PLATFORM
1. All components present
2. Unit set-up as per set-up drawing
3. All bolts and pins positioned, nyloc nuts on bolts, clips in pins
4. Skylarks fitted to platform and secondary steel wire ropes
5. Central yoke box hung on back handrail
6. Wall rollers fitted to front end face
7. Correct steel wire rope end-weights fitted.
8. Restraint ropes present in working platform
9. Hoists bolted to stirrups with HS bolts and Nyloc nuts
10. Hoists greased, if necessary, serviced
11. Sheave bolts in place with nylocs
12. Fall prevention equipment present
OVERHEAD PROTECTION
Protection under platform present. (Barricade work areas as appropriate).
FIRST SET-UP SAFETY CHECKLIST