5.4.2 Mounting the rudder
a) Attach the vertical stabiliser front mounting. It will need spacing from the
SKR22 angle so that when tensioning the bolt it doesn’t pull downwards.
There are some plastic bobbins in the A9 bag that can be used for this plus
plastic spacer washers as required.
b) Attach the rudder to the vertical stabilizer using the three eyebolts
The eyebolts fitted to the rudder itself should have two steel washers
under their heads to stand off the rudder a little or may come with
aluminium saddle washers.
Plastic saddle washers should not be
used in this position.
Figure 104 rudder mounting
– top middle and lower hinge
c) Make sure that the rudder is not touching the stainless-steel elevator joiner
tube when it is deflected from side to side (
25
or so) and the elevators are
moved up and down (
25
or so).
If it is touching you will need to put an additional steel washer under the
eyebolts on the rudder to act as spacers
– but ensure that thread still
protrudes through the nuts..
d) Make sure the fit of the eyebolts is easy and the rudder can be deflected with
no discernible friction.
If the fit is tight and friction is present then the eyebolts need to be
aligned. For up and down alignment do this by removing eyebolts from
the rudder and filing the holes a little as required to bring them into
alignment. For vertical alignment washer may have to be added under
the heads of one or two of the eyebolts. When the rudder is finally fitted
later assemble with grease which will further provide free movement
and protect these steel parts against wear and corrosion.
Summary of Contents for Nynja
Page 1: ...1 Nynja Build Manual 1 4d Nynja Build manual Version 1 4d...
Page 2: ...2 Nynja Build Manual 1 4d Figure 1 tube numbering scheme...
Page 3: ...3 Nynja Build Manual 1 4d Figure 2 Basic frame Skyranger...
Page 4: ...4 Nynja Build Manual 1 4d Figure 3 uncovered Skyranger frame...
Page 60: ...60 Nynja Build Manual 1 4d Figures 65 cable arrangement further overview...
Page 187: ...187 Nynja Build Manual 1 4d Figure 254 heavy duty power wiring schematic Rotax 912...
Page 188: ...188 Nynja Build Manual 1 4d Figure 255 low current wiring schematic Rotax 912...
Page 189: ...189 Nynja Build Manual 1 4d Figure 256 instrument wiring schematic Rotax 912...
Page 207: ...207 Nynja Build manual 1 4d 18 2 One Piece Door Figure 282 one piece door frame...
Page 269: ...269 Nynja Build manual 1 4d...
Page 270: ...270 Nynja Build manual 1 4d 27 2 Wire locking...
Page 271: ...271 Nynja Build manual 1 4d...
Page 272: ...272 Nynja Build manual 1 4d...
Page 273: ...273 Nynja Build manual 1 4d...