11.

 

Position the TT391 Flightline Tester on one of the test points identified in previous step. 

CAUTION 

The Flightline Tester is not weatherproof when the lid is open. Do not 
setup or operate the Flightline Tester in conditions of rain, sleet, etc. 

12.

 

Setup and verify operation of the TT391 Flightline Tester: 

a.

 

Open the chassis lid and remove the lid from the chassis by sliding the lid off of the hinge pins 
(sliding it to the right). The lid "stay" must be removed from the lid before mounting. The stay 
will pop off of the lid. (The stay is the hinged part that props the lid open on the chassis). 

NOTE 

The Patch Antenna may be used without a tripod. The Patch Antenna can 
be held, or secured, and pointed towards the SKYWATCH HP aircraft 
under test 

WITH THE MOUNTING STUD POINT TOWARD THE GROUND

.

 

This 

orientation is critical. 

b.

 

Mount the chassis lid, with the Patch Antenna facing the aircraft, onto a tripod (not included). 
The tripod must be capable of holding the antenna (approximately 2.5 lb) and must provide a 
standard base mounting stud threaded 1/4"-20. A typical tripod mount is shown in Figure 3-4. 

c.

 

If the internal batteries are being utilized, proceed to sub-step f. If the Flightline Tester AC 
Converter Power Supply is to be utilized, proceed to sub-step d.  

d.

 

Connect the AC Converter Power Supply cable connector to the chassis external connector. 

e.

 

Connect the AC Converter Power Supply input power cable connector to one of the following AC 
sources:. 

 

115 Vac, 60 Hz 

 

115 Vac, 400 Hz 

f.

 

Set the Flightline Tester POWER switches to the ON position. 

g.

 

Verify that the LOW indicator is not steady on (it may flash). If the LOW indicator remains on 
(i.e., lit), perform one of the following three options. 

 

Use the AC Converter Power Supply to power the unit. 

 

Recharge the internal batteries. 

 

Replace the internal batteries. 

h.

 

Set the SELF-TEST switch to the 1030 position and verify that the 1030 indicator blinks on for 
1/2 second every 5 seconds. 

i.

 

Set the SELF-TEST switch to the 1090 position and verify that the 1090 indicator blinks on for 
1/2 second every 5 seconds. 

j.

 

Set SELF-TEST switch to center position (off). Set the POWER switch to the OFF position. 

NOTE 

Care should be taken to ensure that the Patch Antenna is connected to 
TT391 connector J1 and NOT J2. IF THE PATCH ANTENNA IS 
CONNECTED TO J2 THE TT391 WILL NOT FUNCTION 
CORRECTLY. 

k.

 

Connect the Flightline Tester coax cable to J3 on the Patch Antenna and to connector J1 in the 
chassis. (J2 should remain capped by the dust cover). 

 

The document reference is online, please check the correspondence between the online documentation and the printed version.

Summary of Contents for SKY899

Page 1: ... 2 All test equipment used in completing these tests shall be calibrated in accordance with the manufacturer s recommendations 3 This section provides checkout information for the SKY899 using the WX 1000 Display If using an alternate display use Appendix F for installation checkout 4 Checkout of the WX 1000 processor should be done in accordance with the procedures detailed in the WX 1000 Install...

Page 2: ...a Traffic Advisory i e a solid circle at nm and Other Traffic i e open diamond at 4 5 nm Both targets will be displayed in level flight at own aircraft altitude i e 00 displayed above the traffic symbol If the indications given in the following procedure except for the Flightline Tester are not obtained refer to the troubleshooting procedures in Chapter 4 If indications given for the Flightline Te...

Page 3: ...ge Calibration will be done during system setup verification and operation Figure 3 3 Standby Screen 3 3 1 System Setup The system configuration can be done using the service menu or it can be downloaded with a previously saved configuration using the Compact Flash Card Both setup procedures are described below and assume familiarity with service menu operation see chapter 4 for operation informat...

Page 4: ...d at a comfortable level then select exit to return to setup menu 5 From the Setup menu select ARINC 429 ports and manually configure each receiver channel Refer to paragraph 4 4 1 4 NOTES 1 It is possible for multiple data inputs barometric altimeter radio altimeter magnetic heading and GPS navigation from one source to be received on one channel e g ARINC 429 superbus Multiple data inputs will b...

Page 5: ...eturn to Service Menu e The Save or Revert menu will appear upon exiting setup menu Select Save Changes to keep current configuration Selecting Revert to Old Settings will cause system to exit the service menu without saving changes 7 To verify changes made to the configuration module turn the SKY899 OFF and then enter the Service Menu see paragraph 4 4 and repeat Step 6 8 Perform system setup ver...

Page 6: ...h altitude and heading sensor Verify data monitors show the correct input changes i e sensing of these signals b If the information is not correct the sensor has failed to communicate with the TRC Check operation of the sensor and connections between the TRC and sensor c Select exit until you return to the Service Menu 4 From the Service Menu select Ground Test see paragraph 4 4 4 5 From the Groun...

Page 7: ... to sub step f If the Flightline Tester AC Converter Power Supply is to be utilized proceed to sub step d d Connect the AC Converter Power Supply cable connector to the chassis external connector e Connect the AC Converter Power Supply input power cable connector to one of the following AC sources 115 Vac 60 Hz 115 Vac 400 Hz f Set the Flightline Tester POWER switches to the ON position g Verify t...

Page 8: ...path distortion see step 1 3 During these tests the SKY899 may detect and display other active targets 4 To obtain a better line of sight it may be necessary to elevate the patch antenna d Set the TT391 POWER switch to the OFF Repeat procedure from each test point Step 15 can be done from the last test point NOTE To prevent SKYWATCH HP from tracking the movement of the test set it is necessary to ...

Page 9: ...are cleared from the aircraft s instruments 2 Turn SKY899 ON The display should show a start up screen similar to one shown in Figure 3 2 3 After approximately thirty seconds observe the STANDBY screen and then press the TEST button soft key 2 4 The display should present a screen similar to that shown in Figure 3 5 Figure 3 5 Self Test Screen 5 If the SKY899 passes the self test the system will r...

Page 10: ...be connected to P1 89 AUDIO_H 2 150 ohm audio systems should be connected to P1 90 AUDIO_L 3 Audio common is connected to P1 91 AUDIO_C NOTE Audio output from the TRC is transformer isolated 7 If SKY899 fails the self test a The SKY899 Failed screen with an error message indicating the type of failure will be displayed b The voice message SKYWATCH SYSTEM TEST FAILED will be enunciated over the coc...

Reviews: