11 Decommissioning
SMA Solar Technology AG
40
MC_BOX_36-BE-en-20
Operating Manual
11 Decommissioning
11.1 Disassembling the Multicluster Box
2. Remove all fastening screws from the kick plates at the front and rear. Set the screws aside.
These screws will be needed later to reattach the kick plates.
3. Remove all sliding panels from the Multicluster Box.
4. Remove all connection cables from the Multicluster Box.
5. Unscrew and remove the fastening screws of the Multicluster Box.
6. Mount the contact hazard protection cover (see Section 7.11, page 35).
7. Close the doors of the Multicluster Box.
9. Reattach the kick plates to the Multicluster Box.
11.2 Storing the Multicluster Box
Α Store the Multicluster Box in a dry place where the ambient temperature is between −25°C and
+60°C.
11.3 Disposing of the Multicluster Box
Α Dispose of the Multicluster Box in accordance with the locally applicable disposal regulations
for electronic waste.
1.
Danger to life due to electric shock
High voltages are present in the Multicluster Box and the multicluster system. Touching live
components results in death or serious injury due to electric shock.
Α Disconnect the multicluster system from voltage sources (see Section 8, page 35).
8.
Danger of crushing if the raised MV Power Platform topples, falls, or sways
Α Transport the Multicluster Box with a forklift truck, pallet truck, or crane
(see Section 6.3.3, page 18).