Sunny Boy 2500U
Installation and Operator’s Manual
SB2500U-11:NE
-
36
-
SMA Regelsysteme GmbH
4.4 Opening and closing of the Sunny Boy
Normally the Sunny Boy operates fully automatically and maintenance-free. Should the
device nonetheless be opened e.g. for
•
upgrading or modification of the Sunny Boy interface
•
control of internal AC-fuse
follow the instructions given below.
Opening of the Sunny Boy
WARNING:
These servicing instructions are for use by qualified personnel
only. To reduce the risk of electric shock, do not perform any sevicing
other than specified in this technical description unless you are qualified to
do so.
When working on the Sunny Boy follow the instructions below:
1. Separate the Sunny Boy from the grid by opening the 240 Volt AC-circuit breaker in
the main fusebox.
WARNING:
Make sure the main 240V breaker in the main utility breaker
box is switched OFF.
2. Switch the DC-breaker in the DC disconnect enclosure OFF.
WARNING:
Wait for approx. 5 minutes until internal voltage has dis-
charged after shutting down the DC-voltage on the Sunny Boy.