14 Troubleshooting
SMA Solar Technology AG
Operating manual
SI44M-80H-13-BE-en-15
172
4. Select
Login
.
5. Call up the menu
Device parameters
.
6. Click on [
Edit parameters
].
7. In the parameter group
User Rights > Access Control
change the password of the desired user group.
8. Select [
Save all
] to save the changes.
14.7
Problems with streaming services
If you use the streaming service in your local network (in which the inverter is also included), there may be interference
to the transfer of data. In this case, the IGMP settings of the inverter can be changed via operating parameters.
• Contact the Service and change IGMP settings in consultation with the Service department.
14.8
Set time for detection of communication failure
If communication between the Sunny Island and the SMA Energy Meter or the Sunny Home Manager is interrupted,
the Sunny Island stops after a certain time. Both multifunction relays then switch to the idle state. As a consequence, the
feed-in operation of the PV inverters is stopped.
The time until this communication failure is detected is adjustable.
Procedure:
1. Select
System & device control > Point of interconnection
.
2. Set the
Communication timeout for measured value acquisition of Energy Meter at point of
interconnection
to a value between 1 s and 30 s (default value: 2 s).