Commissioning
7.1
Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must always perform in the
prescribed order.
A country data set must be set for feed-in operation
To ensure the inverter begins feed-in operation during initial commissioning, a country data set must be set (for
instance via the installation assistant on the user interface of the product, or via a communication product).
If no country data set is set, then feed-in operation will be stopped. This state is signaled by orange glow of the
inverter LED. The power LED and the battery LED are off.
The inverter will automatically start feed-in operation only after the inverter configuration is completed.
Procedure
See
1.
Commission the inverter.
2.
Establish a connection to the user interface of the inverter. The following connection options are available
to choose from:
• Direct connection via Wi-Fi
• Direct connection via Ethernet
• Connection via Ethernet in the local network
3.
Log into the user interface.
The installation assistant opens automatically when logging into the
user interface for the first time.
4.
Set the system-specific basic configuration. Note that the personal
SMA Grid Guard code for changing the grid-relevant parameters
must be available after completion of the first 10 operating hours.
You can request the SMA Grid Guard code via the Online Service
Center.
5.
Make individual parameter settings:
• Set country data set.
• Configure the thresholds for systems for increased self-
consumption
• Set parameters for battery management.
• Set parameters for energy management.
• Set parameters for generator management.
• Set parameters for off-grid systems.
• Set multifunction relay.