Sunny Boy 2000
Technical Description
SB2000-11:EE
- 27 -
SMA Regelsysteme GmbH
Before connecting the PV-panel to the Sunny Boy check the installation is isolated
from earth by:
••••
Determining the DC voltage between protective earth (PE) and the plus and
minus poles of the PV panel.
If you measure stable voltages there is a ground fault in the PV-panel or
its cabling. You can assess where the failure is located from the ratio of
the different voltages measured. It is essential to solve this failure before
continuing the installation!
•
Acquiring the electric resistance between protective earth (PE) and the plus
and minus poles of the PV-panel.
A low resistance (< 2 M
Ω
Ω
Ω
Ω
) shows there is a high-resistance ground fault
of the PV-panel. It is essential to repair this failure before continuing the
installation!
After you have checked the PV-panel is isolated from earth you can establish the
electrical connection to the Sunny Boy. Remove the seal from the plug connectors at
each cable end of the PV-panel and firmly insert them into the Sunny Boy 2000. As
soon as the PV-panel has been connected to the Sunny Boy with the MC
®
plug con-
nectors the internal PV-panel voltage is on.