Sunny Boy 2000
Technical Description
SB2000-11:EE
- 58 -
SMA Regelsysteme GmbH
Only work on the Sunny Boy when it is disconnected from the grid
and sufficiently discharged!
Follow ESD protection countermeasures when modifying the Sunny Boy:
Electronic components are sensitive to electrostatic discharge. To protect them you
have to be on the same electric potential. Discharge the electrostatic charge by
touching the grounded case before touching an electronic component, otherwise you
run a great risk of destroying your electronics.
Work on the inverter always has to be done in the order described:
1. Disconnect the inverter from the grid.
2. Disconnect the inverter from all poles of the PV-panel.
Wait for approximately 30 minutes until internal voltages have
discharged.
Open the device only after the above steps have been taken.