Sunny Boy 2000
Technical Description
SB2000-11:EE
- 20 -
SMA Regelsysteme GmbH
top
T
o
tal hight of Sunn
y Bo
y 2000:
295.50 mm
=
ve
rtical distance of holes:
220.50 mm
=
position of top holes
Distance between top holes 217.50 mm
total width of Sunny Boy 2000: 434.50 mm
+
+
+
Drilling Template Sunny Boy 2000
63.50 mm
Fig. 3.2: Drilling Template
Preparing the Mounting
The Sunny Boy is mounted on its back with three metal straps on a firm sur-
face. Three screws and the corresponding dowels are necessary. The screws
and dowels are not included and have to have a sufficient size. We recommend
6 mm screws and 8 mm dowels.
For outside mounting use stainless steel material
(screws, washers etc.).
The Sunny Boy is mounted to the wall by three metal straps on the back of the de-
vice (see Fig. 3.2).