Sunny Boy 2000
Technical Description
SB2000-11:EE
- 39 -
SMA Regelsysteme GmbH
••••
Reconnect the PV-panel, do not connect the mains voltage!
•
If the red LED is off see ‘A’ - if the LED is on see ‘B’.
+
+
thermally monitored
varistors
PV-panel
connectors
+
1
2
3
1
2
3
1
2
3
1
2
3
Fig. 5.2: Thermally monitored varistors
A
The red LED is off.
At least one of the thermally monitored varistors is defective. We recom-
mend to replace both varistors by original SMA spare parts.
The thermally monitored varistors are only available from the manu-
facturer because they are designed especially for the Sunny Boy in-
verter systems.
B
The red LED is still on. The following must be done:
•
disconnect all poles of the PV-panel from the inverter
Wait at least 30 minutes until all internal voltages have discharged!
•
Remove the short circuits from 2 to 3 in the two connector blocks X2 and
X3. Short circuit the connector 2 in connector block X2 to connector 2 in
connector block X3.