7 Commissioning
Check the following requirements before commissioning:
•
Secure fit on wall bracket / top hat rail
•
Correct country configuration (see section 6.4.2)
•
Correct connection of the AC (grid) cable
•
Full connection of the DC cables (PV strings)
•
Unrequired DC plug connectors in the DC connection area are sealed with caps
•
All housing openings are sealed
•
The lid is securely screwed in place
•
The Electronic Solar Switch is securely plugged
•
The AC distribution is installed correctly
Commissioning procedure
1.
Switch on the line circuit breaker.
2.
If the radiation is sufficient, an illuminated green
LED indicates that feeding is running without
problems. If this is the case, commissioning was
completed successfully.
If the green LED flashes for an extended period,
this may be due to the fact that the DC radiation is
not sufficient.
Measurements can only be made if the DC radiation is sufficient.
3.
The meaning of the illuminated red LED and the meaning of the event numbers on the display
are described in section11.2 „Error Messages” (Page 59).
Summary of Contents for SUNNY BOY 4000TL
Page 6: ...SMA Technologie AG 6 SB40TL_50TL IEN081211 Installation Guide...
Page 16: ...Technical Data SMA Technologie AG 16 SB40TL_50TL IEN081211 Installation Guide Efficiency curve...
Page 73: ...SMA Technologie AG Contact Installation Guide SB40TL_50TL IEN081211 73...
Page 74: ...Contact SMA Technologie AG 74 SB40TL_50TL IEN081211 Installation Guide...