8 Commissioning
SMA Solar Technology AG
Operating manual
SB55-LV-JP-41-BE-en-13
39
8
Commissioning
8.1
Commissioning Procedure
Procedure
See
1.
Commission each inverter.
2.
Establish a connection to the user interface of an inverter.
The following connection options are available to choose
from:
• Direct connection via WLAN
• Connection via WLAN in the local network
• Direct connection via Ethernet
• Connection via Ethernet in the local network
3.
Log into the user interface.
4.
Configure the inverter using the installation assistant.
5.
Save the configuration of the inverter in a file.
6.
Establish a connection to the user interface of each addi-
tional inverter in the system.
7.
Log into the user interface of each additional inverter.
8.
Configure each additional inverter using the configuration
file of the first inverter.
9.
To monitor the PV system and visualize the PV system
data, register in the Sunny Portal and create the system in
Sunny Portal or add devices to an existing system.
https://ennexos.sunnypor-
tal.com or https://www.sun-
nyportal.com
8.2
Commissioning the Inverter
Requirements:
☐ The AC circuit breaker must be correctly rated and mounted.
☐ The product must be correctly mounted.
☐ All cables must be correctly connected.
Procedure:
1. Switch on the AC circuit breaker.