9 Operation
SMA Solar Technology AG
Operating manual
SB55-LV-JP-41-BE-en-13
51
3. Select the menu
User Settings
(see Section 9.3, page 48) on the start page of the user
interface.
4. Select [
Smart Inverter Screen
].
☑ The Smart Inverter Screen has been activated.
9.5
Starting the Installation Assistant
The installation assistant leads you step-by-step through the steps necessary for the initial
configuration of the inverter.
Layout of the installation assistant
A
C
B
Figure 11: Layout of the installation assistant (example)
Position
Designation
Description
A
Configuration steps
Overview of the installation assistant steps. The number of
steps depends on the type of device and the additionally
installed modules. The current step is highlighted in blue.
B
User information
Information about the current configuration step and the
setting options of the configuration step.
C
Configuration field
You can make settings in this field.
Requirement:
☐ When configuring after completion of the first ten feed-in hours or after exiting the installation
assistant, the SMA Grid Guard code must be available in order to change the grid-relevant
parameters (see "Application for SMA Grid Guard Code" at www.SMA-Solar.com).
Procedure:
1. Open the user interface (see Section 9.1, page 43).
2. Log in as
Installer
.