12 Troubleshooting
SMA Solar Technology AG
Operating manual
SB55-LV-JP-41-BE-en-13
65
Event number
Message, cause and corrective measures
105
Grid overvoltage very fast
Corrective measures:
• Check whether the grid voltage at the connection point of the inverter is
permanently in the permissible range.
If the grid voltage is outside the permissible range due to local grid
conditions, contact the grid operator. The grid operator must agree with
an adjustment of the voltage at the feed-in point or with a change of the
monitored operating limits.
If the grid voltage is permanently within the permissible range and this
message is still displayed, contact Service.
202
Grid undervoltage fast
The utility grid has been disconnected, the AC cable is damaged or the grid
voltage at the connection point of the inverter is too low. The inverter has dis-
connected from the utility grid.
Corrective measures:
• Ensure that the circuit breaker is switched on.
• Ensure that the AC cable is not damaged and that it is connected
correctly.
• Ensure that the country data set has been configured correctly.
• Check whether the grid voltage at the connection point of the inverter is
permanently in the permissible range.
If the grid voltage is outside the permissible range due to local grid
conditions, contact the grid operator. The grid operator must agree with
an adjustment of the voltage at the feed-in point or with a change of the
monitored operating limits.
If the grid voltage is permanently within the permissible range and this
message is still displayed, contact the Service.