Installation
SMA
Technologie AG
Page 22
SB1100LV-11:SE2006
Installation Guide
Connecting the AC output with PG13.5
To connect a cable with a maximum cross-section of 13.5 mm², proceed as follows.
1.
Press the sealing ring into the cord grip.
2.
Now slide the pressure screw over the cable first of all, followed by the cord grip
with the sealing ring in it. Now slide the threaded sleeve over the cable.
3.
Now connect the individual conductors to the socket element in sequence.
- Protective earth PE (green/yellow) to the screw terminal
with the earth sign. Make sure that the PE earth wire is
longer than the N and L connected wires.
- Neutral conductor N (blue) to screw terminal 1.
- Live L (brown or black) to screw terminal 2.
- Terminal 3 remains unused.
4.
Make sure the wires are securely connected.
Sealing ring
Cord grip
Threaded sleeve
Cord grip with
sealing ring
Pressure screw
Terminals in the
socket element
Socket element
Connected wires
Threaded sleeve
Cord grip with
sealing ring
Pressure screw
Summary of Contents for Sunny Boy SB 1100LV
Page 2: ......
Page 8: ...Foreword SMA Technologie AG Page 8 SB1100LV 11 SE2006 Installation Guide ...
Page 10: ...Safety instructions SMA Technologie AG Page 10 SB1100LV 11 SE2006 Installation Guide ...
Page 32: ...Installation SMA Technologie AG Page 32 SB1100LV 11 SE2006 Installation Guide ...
Page 44: ...Technical data SMA Technologie AG Page 44 SB1100LV 11 SE2006 Installation Guide ...
Page 50: ...Replacing the varistors SMA Technologie AG Page 50 SB1100LV 11 SE2006 Installation Guide ...
Page 58: ...The communications interface SMA Technologie AG Page 58 SB1100LV 11 SE2006 Installation Guide ...
Page 61: ......