6.3 Commissioning
You can commission the Sunny Boy when:
•
the housing cover is securely screwed shut,
•
the AC (grid) cable is connected correctly,
•
the DC cables (PV strings) are fully connected and the unused DC plug connectors
on the bottom of the housing are closed using the protective caps.
How to Commission the Inverter
Check the string voltages again to make sure they are within the limits stated in section
5.2 "PV Generator Requirements" (Page 15). If the input voltage is too high, contact the
planner / installer of the PV generator for assistance.
If despite checking the string voltages the LED signal occurs again when the PV
generator is connected to the Sunny Boy, disconnect the PV generator from the Sunny
Boy again and contact SMA Technologie AG (see section 12 "Contact" (Page 63)).
1.
First of all, switch the line circuit breaker to the
"on" position.
2.
Now look at the LED display and consult the
table on the following page to check whether the
Sunny Boy is in a fault-free and appropriate
operating mode. If this is the case,
commissioning was successfully completed.
Warning!
If the bottom yellow LED flashes four times at intervals of one second, the
grid voltage and the PV generator must be immediately disconnected
from the Sunny Boy! There is a risk of damage to the inverter resulting
from excessive DC input voltage!
On
Summary of Contents for Sunny Boy SB 2500
Page 2: ......
Page 6: ...Explanation of the Symbols Used SMA Technologie AG Page 6 SB25_30 11 SE0307 Installation Guide...
Page 10: ...Safety Instructions SMA Technologie AG Page 10 SB25_30 11 SE0307 Installation Guide...
Page 20: ...Installation Requirements SMA Technologie AG Page 20 SB25_30 11 SE0307 Installation Guide...
Page 62: ...The Communication Interface SMA Technologie AG Page 62 SB25_30 11 SE0307 Installation Guide...
Page 65: ......