Fig. 2.8:
AC connection socket
•
Connect the main 120 V AC-breaker box to the Sunny Boy by a 1/2“ conduit.
•
Insert the conduit fitting in the very right opening of the Sunny Boy. Fasten the fit-
ting on the inside of the Sunny Boy with the nut.
•
Pull the wires through the conduit into the interior of the Sunny Boy.
•
Connect the wire L1 to the terminal labeled L in the Sunny Boy (see Fig. 2.8).
•
Connect the wire N to the terminal labeled N in the Sunny Boy.
•
Connect the equipment-grounding conductor to the terminal labeled PE in the
Sunny Boy.
•
Torque wires with torque of 35 in-lb.
•
Ensure all connections are correctly wired and properly torqued.
L1
N
Ground
AC conduit and wiring