First switching on
Please follow the order described when commissioning the device.
Fig. 3.1: Diagram of commissioning” provides a sequence chart for commissioning.
NOTE: Following this procedure you will make sure that the PV-panel is
isolated from earth and the GFDI-fuse is not defective without using any
additional measuring instrument.
•
Remove the GFDI-fuse from the Sunny Boy (see Fig. 2.5).
•
Connect the grid voltage by switching ON the main 120V AC-circuit breaker of the
supply lead.
•
Uncover the PV-panel. At sufficient insolation the PV-panel produces the required
output power for supplying the Sunny Boy.
•
Switch ON the DC-circuit breaker in the DC disconnect enclosure . Now the Sunny
Boy is supplied with the DC-voltage and starts to operate.
•
If the PV-panel is isolated from earth first the yellow and red LEDs and after
approx. 20 seconds only the red LED is on at the Sunny Boy. If you have commu-
nication equipment you will be displayed the “GFDI-Fuse open” failure. Should
both
the red
and
the yellow LEDs still be on there is a ground fault of the PV-
panel. If you have communication equipment you will be displayed the “EarthCur-
rentMax” failure. The ground fault has to be removed. Then the commissioning
procedure described above has to be repeated until only the red LED is on.
•
When you have made sure the PV-panel is isolated from earth (only red LED on)
switch the DC-breaker OFF.
•
Wait until the LEDs at the device have turned off (max. 5 minutes).
•
Screw the GFDI-fuse into the fuse holder at the Sunny Boy again.
•
Switch the DC-breaker ON again so that the Sunny Boy is supplied with the DC-