4.4 Opening and closing of the Sunny Boy
Normally the Sunny Boy operates fully automatically and maintenance-free. Should the
device nonetheless be opened e.g. for
•
upgrading or modification of the Sunny Boy interface
•
control of internal AC-fuse
follow the instructions given below.
Opening of the Sunny Boy
WARNING: These servicing instructions are for use by qualified per-
sonnel only. To reduce the risk of electric shock, do not perform any
sevicing other than specified in this technical description unless you
are qualified to do so.
When working on the Sunny Boy follow the instructions below:
1. Separate the Sunny Boy from the grid by opening the 120 Volt AC-circuit breaker
in the main fusebox.
WARNING: Make sure the main 120 V breaker in the main utility
breaker box is switched OFF.
2. Switch the DC-breaker in the DC disconnect enclosure OFF.
WARNING: Wait for approx. 5 minutes until internal voltage has dis-
charged after shutting down the DC voltage on the Sunny Boy.