6 Maintenance
SMA Solar Technology AG
Maintenance Manual
SCCPXT-E7-WA-en-37
44
Task
See
Checking the AC disconnection unit
Manufacturer documentation
(see Section 1.7, page 7)*
* In deviation to the maintenance interval specified by ABB, the maintenance interval of 24 months stated in this documentation applies.
Maintenance under voltage-free conditions
Task
See
Perform the visual inspection
Analyzing the temperature indicators
Cleaning the ventilation plate
Clean the air duct, ventilation grids and air intake.
Checking the interior
Checking the fuses/disconnection blades
Checking the bolted connections
Cleaning the heating elements of the low-temperature range option
Check the labels
Checking the inverter surface
Maintenance work with supply voltage present
Task
See
Checking the DC switchgear
Manufacturer documentation
(see Section 1.7, page 7)*
Check the fans
Checking the heating element and the hygrostat
Checking the heating element for low-temperature option
Checking the function of the UPS
* In deviation to the maintenance interval specified by ABB, the maintenance interval of 24 months stated in this documentation applies.
6.3
Repair Schedule and Spare Parts
6.3.1
Information on Repair Work
Spare parts
Only original parts or parts recommended by SMA Solar Technology AG are to be used as spare parts when
replacing components.
Spare parts can be identified via the reference designation and the circuit diagram. The spare-parts list includes
the article numbers of each spare part. For information on a specific article number, contact us (see Section 9
"Contact", page 68).
Summary of Contents for SUNNY CENTRAL 1000CP XT
Page 70: ...www SMA Solar com...