4 Disconnecting and Reconnecting
SMA Solar Technology AG
Maintenance Manual
SCCPXT-E7-WA-en-37
28
5. Open the measurement and disconnect terminals.
6. Ensure that no voltage is present.
7. Cover or isolate any adjacent live components.
4.3
Reconnecting the Inverter
4.3.1
Reconnecting the Supply Voltage at the Inverter
1. Close the measurement and disconnect terminals.
2. Switch on the motor-protective circuit-breakers of the grid
monitoring.
3. Connect any additional external voltage.
4. If the supply voltage has been disconnected downstream from the circuit breaker, switch the external circuit
breaker of the supply voltage on.
Tip: The external circuit breaker of the supply voltage is usually located in a subordinate distribution station.