Installation Requirements
SMA
Technologie AG
Page 16
SC-100-13:SE2407
Installation manual
Figure 5.2:
Installation of the SC100 Outdoor with concrete foundation slab
The inverter cabinet must be installed on a level surface. Any existing unevenness,
depressions or slope must be corrected prior to installation.
When pouring the foundation, keep in mind that the cables and conduits should enter
the inverter from underneath. This means that suitable conduits or cable feed-throughs
should be installed prior to pouring.
Pouring and structural inspection of the foundation slab should be performed on-
site.
The cable must be routed into the inverter from below.
The cable routing through the removable base plates in the Sunny Central is
displayed in
figure 5.3
.
The control voltage and communication cables must be installed separately.
Concrete foundation slab
Concrete foundation slab