Opening and Closing
SMA Solar Technology AG
58
SSMUS-TUS094511
Technical Description
10 Opening and Closing
10.1 Opening Sunny Central String-Monitor
1. Switch off the Sunny Central as described in the Sunny Central installation guide.
2. Wait 5 minutes before opening the Sunny Central String-Monitor.
3. Open the Sunny Central String-Monitor.
4. Ensure that no voltage is present in the system.
5. Open the fuse holders.
6. Pull the fuses out of the fuse holders and lay them
aside.
☑ The Sunny Central String-Monitor is opened.
DANGER
Risk of electric shock when opening the Sunny Central String-Monitor under load.
Death or serious injuries.
• Cover the PV modules with an opaque (dark) material.
DANGER
High voltages are present in the Sunny Central String-Monitor. Death or serious injury due
to electric shock.