10 Operating the Sunny Island
10.1 Switching On and Off
10.1.1 Switching On/Starting
Start the island grid system with the Sunny Island
Proceed as follows:
1.
Insert the NH fuse in the BatFuse or close the BatFuse's DC disconnector.
2.
Press the DC start key on the Sunny Island
Wait approx. 20 to 30 seconds.
The Sunny Island is switched on
3.
Press and hold the start / stop button on the Sunny Island.
During the start procedure the inverter LED goes from orange to green.
4.
Let go of the start / stop button
The inverter LED glows green continually.
The Sunny Island is in operation.
WARNING!
Danger due to incorrect wiring of the island grid system
Only qualified electricians should carry out the first commissioning. Check the island grid
system beforehand for
•
correct electric cabling and connections
•
voltages and polarities
Information
The island grid system can also be operated without an external display (Sunny Remote
Control 1). In this case the Sunny Island works only with the default parameters (see
chapter 17.2 "Adjustable System Parameters" (Page 166)).