Additionally the remaining times for e.g. crank, warm up phases etc. will be displayed
in the last line when this menu is entered.
Name Description
State
Operating state of generator
Fail
Fail state of generator
601_GenSet Oper Auto:
The generator is automatically started and stopped by the
Sunny Island.
Man. Start:
The generator is started immediately*.
Man. Stop:
The generator is stopped immediately*.
Man. Ackn.:
Waiting times due to failures or parameters are finished.
* However, parameterized times are kept to.
“PARGEN” (3+6)
Name Description
602_GenSet Type None:
No generator present in island grid
Grid forming:
Generator is grid-forming.
Mains:
Sunny Island is operated on the public utility grid.
BHKW-Mains
Sunny Island is operated together with an ecopower CHP and
on the public utility grid
BHKW-Island
Sunny Island is operated together with an ecopower CHP
Mains form
Sunny Island is operated together with a grid-forming genera-
tor and on the public utility grid
fast Grid form
Generator is grid-forming and it is switched between the gen-
erator and the Sunny Island without interruption (special in-
stallation measures are necessary for this)
fast Mains
The Sunny Island is operated on the public utility grid and it is
possible to switch from the Sunny Island as grid-former to the
public utility grid without interruption. (special installation
measures are necessary for this)
fast Mains form
The Sunny Island is operated together with a grid-forming
generator and on the public utility grid. Switching takes place
without interruption (special installation measures are neces-
sary for this)
DroopGen
The Sunny Island is operated together with a generator capa-
ble of droop characteristics in droop mode.
DroopMains
The Sunny Island is operated together with a utility in droop
mode.
DrpGenMains
The Sunny Island is operated together with a generator capa-
ble of droop characteristics and a utility in droop mode.
BHKW-Isl-Term
Sunny Island is operated together with the ecopower CHP. In
contrast to “BHKW-Island”, the Sunny Island will not switch off
the CHP when no more electrical power is required. Thus, the
ecopower CHP will be able to provide as much thermal en-
ergy as required