Sunny Island 4500
Installation & Operating Instructions
BWRI45-13-EE0304
- 113 -
SMA Regelsysteme GmbH
“PARGRD“ (3+4)
Name Description
401_Phase
Mode
1Phs_Single:
single-phase operation, device is single device
1Phs_Psingle:
single-phase parallel operation with one battery per device
(no grid and generator possible!!)
1Phs_Mstr2:
single-phase parallel operation with “two devices with one sin-
gle battery pack”, device is master
1Phs_Mstr3:
single-phase parallel operation with “three devices with one
single battery pack”, device is master
1Phs_Slv2:
single-phase parallel operation with “two or three devices with
one single battery pack”, device is slave 2
1Phs_Slv3:
single-phase parallel operation with “three devices with one
single battery pack”, device is slave 3
3Phs_Mstr1Set: three-phase operation, device is master (L1)
3Phs_Slv1L2:
three-phase operation, device is slave (L2)
3Phs_Slv1L3:
three-phase operation, device is slave (L3)
402_Uconv nom
200 ... 260 V:
setpoint AC voltage the Sunny Island is to supply as grid-
former (RUN_U)
403_Fconv nom
40 ... 70 Hz:
setpoint AC frequency the Sunny Island is to supply as grid-
former (RUN_U)
404_Uext nom
150 ... 260 V:
nominal AC voltage (RUN_I)
405_Uext min
150 ... 260 V:
minimum AC voltage
406_Uext max
150 ... 260 V:
maximum AC voltage
407_Fext nom
40 ... 70 Hz:
nominal AC frequency, Sunny Island operates grid-tied
(RUN_I)
408_Fext min
40 ... 70 Hz:
min. AC frequency
409_Fext max
40 ... 70 Hz:
max. AC frequency
411_Iac chrg mx
0 ... 16 A:
max. current which the Sunny Island may take from the AC
grid in grid-tied operation (RUN_I, battery is charged thereby)
Table 8.2:
Settings in menu “PARGRD“ (3+4)