Sunny Island 4500
Installation & Operating Instructions
BWRI45-13-EE0304
- 135 -
SMA Regelsysteme GmbH
Table 9.3:
Menu “DATALL“ (1-2), password level: 0
“DATALL“ (1-2)
Name Description
Mode
Current operating mode
Pext Sum
Total of active generator power (three phases)
If an “ecopower Mini-BHKW” is installed this equals the sum of the Sunny Is-
land’s power and the power of the CHP unit, as received from by the Sunny Is-
land on its COM3 port.
Bat State
Current battery state (see Chapter 2.2.2)
SOC act
Actual battery state of charge (in per cent)
Pbat Sum
Total battery power (three phases)
Ibat Sum
Total battery current (three phases)
GenState
Operating state of the generator
GenFail
Error of the generator
K1 State
Switch state of relay K1
K2 State
Switch state of relay K2
K3 State
Switch state of relay K3
K4 State
Switch state of relay K4
K5 State
Switch state of relay K5
K6 State
Switch state of relay K6
K7 State
Switch state of relay K7
K8 State
Switch state of relay K8
Fext
Frequency at Generator / Mains sync. input
Uext eff
RMS value of voltage at Generator / Mains sync. input
Iext eff
RMS value of current at Generator / Mains current input
Pext
Power of generator connected to Generator / Mains sync. and current inputs
If an “ecopower Mini-BHKW” is installed this equals the power of the CHP unit,
as received from by the Sunny Island on its COM3 port.
Ubat mean
Mean value of battery voltage
Ibat mean
Mean value of battery current
Pbat mean
Mean value of battery power
Tbat mean
Mean value of battery temperature
Fconv
Current AC output frequency
Uconv eff
Current AC output voltage
Iconv eff
RMS value of current AC output current
Pconv
Current AC active power Sunny Island
Sconv
Current AC apparent power Sunny Island
SOC diff
Estimated error of the calculated actual battery state of charge (“SOC act”)