Sunny Island 4500
Installation & Operating Instructions
BWRI45-13-EE0304
- 199 -
SMA Regelsysteme GmbH
„PARALL“ (3+9)
Parameter Unit
Min.
Max.
Default
Description
601_GenSet Oper
(A)
0
3
0
0: Auto:
The generator is automatically
started and stopped by the
Sunny Island.
1: Man. Start:
The generator is immediately*
started.
2: Man. Stop:
The generator is immediately*
stopped.
3: Man. Ackn:
Waiting times due to failures or
parameters are finished.
* However, parameterized times are kept to.
602_GenSet Type
(A)
0
13
0
0: None:
No generator present in island
grid
1: Grid forming: Generator is grid-forming.
3: Mains:
Sunny Island is operated on the
public utility grid.
4: BHKW-Mains Sunny Island is operated to-
gether with an ecopower CHP
and on the public utility grid
5: BHKW-Island Sunny Island is operated to-
gether with an ecopower CHP
6: Mains form
Sunny Island is operated to-
gether with a grid-forming gen-
erator and on the public utility
grid
7: fast Grid form Generator is grid-forming and it is
switched between the generator
and the Sunny Island without in-
terruption (special installation
measures are necessary for this)
8: fast Mains
The Sunny Island is operated on
the public utility grid and it is pos-
sible to switch from the Sunny Is-
land as grid-former to the public
utility grid without interruption.
(special installation measures are
necessary for this)
9: fast Mains form The Sunny Island is operated
together with a grid-forming gen-
erator and on the public utility
grid. Switching takes place with-
out interruption (special installa-
tion measure are necessary for
this)
10: DroopGen
The Sunny Island is operated to-
gether with a generator capable
of droop characteristics in droop
mode.