Sunny Island 4500
Installation & Operating Instructions
BWRI45-13-EE0304
- 88 -
SMA Regelsysteme GmbH
Parameter Default
Description
512_Acid Pump
Not installed
Only for lead storage battery with liquid electrolyte:
Not installed
Electrolyte circulation pump not installed
Installed
Electrolyte circulation pump installed
By selecting “Installed“, the electrolyte circulation pump is
switched on depending on settings of parameters 513 to 516. Ir-
respective of battery values, however, there is at least one circu-
lation and 9 circulations maximum per day.
602_GenSet
Type
None
None:
No generator present in island grid
Grid forming:
Generator is grid-forming.
Mains:
Sunny Island is operated on the public utility
grid.
BHKW-Mains
Sunny Island is operated together with an eco-
power CHP and on the public utility grid
BHKW-Island
Sunny Island is operated together with an eco-
power CHP
Mains form
Sunny Island is operated together with a grid-
forming generator and on the public utility grid
fast Grid form
Generator is grid-forming and it is switched be-
tween the generator and the Sunny Island with-
out interruption (special installation measures
are necessary for this)
fast Mains
The Sunny Island is operated on the public util-
ity grid and it is possible to switch from the
Sunny Island as grid-former to the public utility
grid without interruption. (special installation
measures are necessary for this)
fast Mains form The Sunny Island is operated together with a
grid-forming generator and on the public utility
grid. Switching takes place without interruption
(special installation measures are necessary for
this)
DroopGen
The Sunny Island is operated together with a
generator capable of droop characteristics in
droop mode.
DroopMains
The Sunny Island is operated together with an
utility in droop mode.
DrpGenMains
The Sunny Island is operated together with a
generator capable of droop characteristics and
a utility in droop mode.
BHKW-Isl-Therm Sunny Island is operated together with the eco-
power CHP. In contrast to “BHKW-Island” the
Sunny Island will not switch off the CHP when
no more electrical power is required. Thus, the
ecopower CHP will be able to provide as much
thermal energy as required.
603_GenSet Inte
None
None:
No generator start via Sunny Island
Type 1:
Autostart, relays K1+K2
Type 2:
3 contacts Run / Start, relays K1, K2, K6