9 Switching On and Off
9.1 Switching On
1. Check the following requirements:
– correct electrical connections
– voltages and polarities
2. Switch the DC circuit breaker of the Sunny Island to "ON".
☑ The display light of the Sunny Island switches on.
☑ The Sunny Island initiates the start-up phase. The
notifications shown here are displayed. The last
notification is displayed as soon as the start-up
phase is completed.
3. To change settings in the QCG, manually start the QCG.
Press and hold down <ENTER> until the Sunny Island beeps three times.
☑ The QCG is started and the notification
displayed here is shown.
Systems with several Sunny Island inverters
Switch on the slaves
before
you switch on the master. To do this, proceed as follows.
"250.01 AutoStr" Parameter
Even with the "250.01 AutoStr" parameter set, the Sunny Island must be manually started after
each time the device is switched on using the DC circuit breaker.
SIBFSBOOT V1.004
SI5048
@SMA 2009
01#StartMenu
Start System