SMA America, LLC
6 Electrical Connection
Technical description
SI4548_6048-US-TB_en-13
41
6.2 DC Connection
6.2.1 Safety Precautions/Conditions
Connect a suitable battery to the DC side (see Section 22 "Technical Data", page 225).
The DC connection must be made in accordance with all locally applicable directives and regulations.
6.2.2 Cable Dimensioning
Function impairments of devices on the DC busbar.
The Sunny Island is
not
suitable for use with DC supply grids. Function impairment can occur on
devices installed on the DC side of a Sunny Island with cables exceeding 98 ft. (30 m) and with a
flexible connection.
• Only use fixed installations.
• Do not use cables of lengths greater than 98 ft. (30 m) between the Sunny Island and the
battery and/or DC device.
Danger to life due to chemical burns in the event of leaking acid
Acid can escape in the event of improper handling of the battery.
• Observe all safety indications and warnings provided by the battery manufacturer.
• Use special (insulated) tools to mount and install the battery.
• Provide sufficient air supply in the room in which the battery is. When gases are produced by
the battery, these cannot be allowed to collect.
Keep the lines to the battery as short as possible.
The battery cables should be as short as possible. Long cables and insufficient cable diameters
reduce the system efficiency as well as the overload capacity. Do not lay the battery lead under
plaster or in armored plastic pipes.
Selection of the cable cross-section
SMA recommends choosing cable cross-sections greater than those given by
National Electrical Code
®
310.15 when the cable lengths exceed 33 ft. (10 m).
Summary of Contents for Sunny Island 4548-US
Page 2: ......
Page 14: ......
Page 240: ...www SMA Solar com SMA Solar Technology SMA America LLC www SMA America com...