Sunny Island Installation and Operating Instructions
BWRI33-12:EE
- 156 -
SMA Regelsysteme GmbH
External charge of the battery
In plants with a scarce battery storage capacity and without a motorized generator,
i. e. where the only feeders are photovoltaic or wind generators, it may become nec-
essary to have the battery recharged by a mobile generator. This can be the case
when unfavorable weather conditions persist for a longer time period.
For this purpose the operator can use a special terminal box available from SMA as
an accessory (SMA order name “SI-GENCASE.01“) which can be firmly installed in
the plant. The circuit diagram is shown in Fig. 16.5. The figure also shows the con-
nection of an external generator in different operating modes and includes instruc-
tions for operation.
According to the current configuration, it may be necessary to change several pa-
rameters, so that the following settings apply:
Parameter Value
401_Phase Mode
1Phs_Single (see chapter 8.4)
602_GenSet Type
Grid forming
603_GenSet Interf
Typ 1
702_Man K2
AUTO
Table 16.1: Setting for the external charge of the battery
In addition, the automatic generator control of the Sunny Island must not be deacti-
vated (menu „GENSET“ (2-2), see chapter 7.2).