Parameter changes should always be made in standby mode. Other-
wise the corresponding operating values are changed as well imme-
diately after pressing [ ENTER ]. Faulty entries cannot be corrected
fast enough and may lead to damages in the plant!
The settings defined will be maintained even if the Sunny Island is
switched off. Therefore you do not have to enter all plant settings again
e. g. after a battery change.
The individual configuration procedures are described in detail in the following chap-
ters.
6.1 First Configuration (“New System“)
The first configuration of the Sunny Island in a new plant or a plant that has been
drastically modified should be made by selecting the menu item “New System“ in the
“INIT“ (0-0) menu. To do so you require the password for “level: 1“ (installer).
After switching on the DC fuse of the Sunny Island you will reach the “INIT“ (0-0)
menu (as described in chapter 5) where you select the menu item “New System“ with
the arrow keys and confirm it with [ ENTER ]. Now enter the password for “level: 1“
(installer).