ROOF ASSEMBLY CONT...
13
= Clout
= Screw
STEP 5:
•
Place barge flashings on roof at end of shed ensuring
the diagonal trimmed end is facing out. (See diagram
on pg 5)
•
Rivet the Barge Flashings to the roof and the side
wall, using four rivets on top of barge and four into the
side (
fig.3
).
STEP 4:
•
Position the second Roof Sheet, and rivet to first roof sheet as
shown.
•
Fasten off as per Step 2.
•
Rivet and nail/screw off the remaining Roof Sheets, ensuring the
ribs line up with the front Roof Sheets and the back Wall Sheets.
STEP 3:
•
Position 1 x roof sheet so that the top of the sheet is at the
centre of the Ridge Beam and the side of the sheet over hangs
the end of the Ridge Beam and the Top Plate by 15mm.
•
Ensure the Ridge Beam and the Top Plate are straight.
•
Nail/screw 4 x corners of the Roof Sheet as shown, ensuring
the ribs on the Roof Sheet line up with the front Roof Sheet and
the back Wall Sheet. Fasten off the first sheet.
STEP 6:
•
Rivet the 2 Ridge Caps together using 4 rivets, so
total flashing is 2.550m long. Rivet the Ridge
Flashing to the centre of the roof using 8 x rivets
as shown (
fig.2
).
FRONT WALL
SIDE
WALL
BACK WALL
TOP PLATE
BOTTOM PLATE
SIDE
WALL
RIDGE BEAM
fig.2
fig.1
SIDE
WALL
FRONT WALL
BACK WALL
SIDE
WALL
TOP PLATE
BOTTOM PLATE
SIDE
WALL
FRONT WALL
BACK WALL
SIDE
WALL
TOP PLATE
BOTTOM PLATE
fig.3
X 4
X 4
Barge
Spouting
fig.4
STEP 7:
•
Place spouting in position and rivet to Barge Flashings
at each end and rivet to roof sheets (1 rivet per 1 sheet)
(fig.4).