1.
Measure the inside of the file drawer
from front to back. This will determine
the length of the Metal Side Rails.
2.
Measure two
Metal Side Rails (B).
3.
If necessary to shorten
Metal Side
Rails
, place pliers next to indentation
closest to the length you need, bend
back and forth until rail breaks. Use
file to soften edges, if needed.
4.
Place each end of a
Metal Side Rail
(B)
into a
Black Plastic Slide Insert
(E),
leaving a small portion of the Side
Rail extending beyond the Plastic side
piece, as shown. Set aside
5.
Remove
Black Plastic Corner Pieces
(
D
) from tree and place
Corner Piece
D1 (D)
on one end of a
Tie Rod (A)
,
and
Corner Piece D2 (D)
on the other
end.
6.
Lightly tap
Corner Pieces
(D)
onto
Tie
Rod (A)
until it will go no further.
7. Place one end of
U frame(C)
into
Corner Piece (D1)
and one end into
Corner Piece (D2).
8. Lightly tap
Corner Pieces (D)
onto
U frame(C)
until it will go no further.
9. Repeat
Steps 5 through 8
You will now have the end components of the Hanging Folder Frame.
10. Place the
Black Plastic Slide Inserts
(E)
on Metal Side Rails into the
openings of the
Black Plastic Corner
Pieces DI & D2.
11. Slide
Black Plastic Slide Inserts (E)
in
or out of
Corner Pieces (D)
to adjust
for letter, legal or A4 hanging folders.