SETUP INSTRUCTIONS AND PRE-OPERATION CHECKLIST FOR 

SNAPPER GROUNDS CRUISER UTILITY VEHICLE 

 

INTRODUCTION: These instructions cover the setup of the Snapper Grounds Cruiser utility vehicle.  Complete 
each step carefully.  A checklist has been provided.  It is very important to verify and record each item on the 
list prior to placing the machine into service. The dry weight of the machine you are about to setup is 1,230 lb. It 
is strongly recommended that you use an overhead hoist when lifting the machine. The capacity of the device 
used for lifting must exceed the weight of the machine.  DO NOT work on the machine until properly blocked 
and secured to prevent it from falling. If an overhead hoist is not available, you may have to remove boards 
from the crate bottom to gain access with floor type jacks. 
 

WARNING 

DO NOT attempt any adjustments, maintenance or 
service with the engine running. STOP engine. Set 
park brake. Shift transmission to neutral and 
remove key. Remove spark plug wire from spark 
plug and secure wire away from spark plug. Engine 
and components are HOT. Avoid serious burns, 
allow all parts to cool before working on machine. 

 

STEP 1 
INSTALL REAR TIRES 

The machine is securely attached to the crate bottom at 
each wheel location. See Figure 1.1. The four steel 
plates must be removed before lifting the machine.  The 
device used to lift the machine must have a capacity 
greater than 1230 lb. The cargo bed is attached to the 
frame of the machine with plastic straps. Carefully 
remove the straps and set the cargo bed aside for 
installation later. 
 

 

 

FIGURE 1.1 

 
1.  Loosen only, two lug nuts at left and right rear 

wheel hubs. 

2.  Remove the four bolts securing the left and right 

support plates to the crate bottom. 

3.  Lift machine, at the rear hitch, only high enough to 

allow tire installation. Block machine securely to 
prevent it from falling. Remove support plates. 

4.  Check castle nuts to insure that the cotter pins have 

been fully inserted and have at least one leg bent to 
secure in place. 

5.  Install left and right rear tires and secure each with 

5 lug nuts. NOTE: The tires are directional.  Install 
with valve stem out and the points of the chevron 
treads pointing forward.  See Figure 1.2.  

 

 

 
 
 

FIGURE 1.2 

 
6.  Remove blocks and lower rear of machine. 
7.  Torque lug nuts to 75 ft-lb using sequence shown.  

See Figure 1.2. 

 

STEP 2 
INSTALL FRONT BUMPER 

The bolts used to attach the front bumper to the 
machine are already installed in the front frame. The 
bumper can be used to lift the weight of the front of the 
machine. The mounting hardware must be tightened 
securely (30 ft-lb). 
1.  Place bumper over four bolts at front of frame. Note 

orientation, flat side of side plates towards bottom 

2.  Attach using (4) 3/8-16 flange lock nuts. 
3.  Torque nuts to 30 ft-lb. 
 
 
 
 
 
 

INSTRUCTION No. 7-4510 (I.R. 5/3/01) 

LUG NUTS 
(LOOSEN ONLY) 

REMOVE 

POINTS OF TREADS POINTING TOWARD FRONT OF VEHICLE. 

1

4

2

5

3