SOLA 4000 - Installation and Initial Start-Up
JUE 401265
15
1
INSTALLATION
1.1 Mechanical Installation
Equipment Delivery and Storage
After delivery, check equipment for any damage that may have
occurred during shipment. The shipper and your SOLA agency
must be notified in writing about damages due to shipment, includ-
ing a detailed description of visual defects. If you do not wish to
install the equipment immediately, please observe the following
storage recommendations:
• Store equipment in a vertical position in a well conditioned
room, protected against humidity. Do not store the equipment
in close proximity to frequently used passageways and keep it
away from movable parts.
• If the UPS system is already unpacked, please ensure storage
in a clean environment protected from dust, away from heat
sources.
Handling the UPS System
The UPS can be simply lifted and moved by means of a lifting
truck or a fork lifter for 80-120kVA units. For 10-60kVA units,
remove the front side and rear side base sheets and attach two
angle irons with 8MA bolts to the right front and rear side of the
UPS. The UPS can now be moved with a lifting fork. Remove the
angle irons when the UPS is set in the correct position.
Caution:
Secure equipment against being knocked over
Setting Up
The UPS system should be installed in a dry, clean and lockable
room. Provisions have to be made to remove heat created by the
system. Under all installation conditions, the unrestricted flow of
cooling air must be assured.
1 Installation