8.  Operation

 • Prior to connecting the PV system to the grid, make sure the entire system has been checked, tested and approved in accordance 

with the applicable regulations.

 • Depending on local regulations and utility policies, connection to the grid and start up of the PV system may only be performed by 

authorized personnel.

9.  Maintenance

A monthly visual check is highly recommended in order to maintain the efficiency of SF modules and the security of the mounting.

 • Remove any dirt, fallen leaves or bird droppings from the surface, and check that there is no damage to the surface. Do not use 

detergent or chemicals for cleaning dirt off SF modules as it may damage the modules and result in degradation of insulation.

 • Do not use hard brushes or any other hard materials; use only soft cloths or sponges for removing dirt from the SF modules surface.

 • When replacement parts are required, be sure the installer/servicer uses parts specified by the manufacturer with the same  

characteristics as the original parts. Unauthorized substitutions may result in fire, electric shock, or other hazard.

 • Stop using SF modules when any damage or unusual phenomena are observed. Have them immediately replaced or removed by a 

qualified technician.

10. Disposal

SF modules must be disposed of in a responsible manner. Please contact your local supplier or disposal company for further  
information. For health and safety reasons, SF modules should not be disposed of with household garbage, and must be dealt with  
in accordance with local codes and regulations.

Solar Frontier is a member of PV Cycle, marking its commitment to the environment and public safety.  
PV Cycle’s initiatives can be found at: http://www.pvcycle.org/

Summary of Contents for SF140-S

Page 1: ...Solar Frontier Europe GmbH Data Sheet and Installation and Maintenance Manual SF140 S SF145 S SF150 S SF155 S SF160 S SF165 S SF170 S ENGLISH...

Page 2: ...2...

Page 3: ...id from August 2013 It replaces all previous changes made to this document Content 1 About this Manual 4 2 General Information 4 3 Technical Data 4 3 1 Electrical Characteristics 4 3 2 Module Performa...

Page 4: ...SF155 S SF160 S SF165 S SF170 S Nominal power Pmax 140 W 145 W 150 W 155 W 160 W 165 W 170 W Power tolerance 5 W 0 W Open circuit voltage Voc 107 0 V 107 0 V 108 0 V 109 0 V 110 0 V 110 0 V 112 0 V S...

Page 5: ...hould not exceed 7 A under any circumstances UL Modules installed in parallel will be provided with the listed maximum series fuse as specified 3 5 Mechanical Data Dimensions L x W x H 1 257 x 977 x 3...

Page 6: ...5 31 1 225 31 1 225 30 12 13 5 35 35 30 372 5 372 5 454 5 454 5 566 5 598 5 5 934 2 21 5 21 5 548 5 120 35 0 5 977 2 90 444 28 2 568 5 5 Mounting holes 2 x Grounding 2 x 4 4 x 8 5 4 x 6 6 Mounting hol...

Page 7: ...circuit voltage must never exceed the maximum system voltage including in low temperature conditions Leakage currents could create a shock hazard or fire Do not disconnect operational modules or elect...

Page 8: ...temperature range indicated in the module s technical specifications 6 3 Module Handling Instructions Do not disassemble or modify SF modules This may result in an electric shock fire or other accide...

Page 9: ...oduction Modules can be installed horizontally landscape or vertically portrait Maintain a space between SF modules and the roof This will allow air to circulate cooling the module and allowing conden...

Page 10: ...0 Pa 50 lbs ft2 to the front and back of the module UL 1 600 Pa 33 4 lbs ft2 to the front and back of the module 1 5 times the design load is applied to the module during UL testing 2 400 Pa 50 lbs ft...

Page 11: ...inimum TUV 2 400 Pa 50 lbs ft2 to the front and back of the module UL 1 600 Pa 33 4 lbs ft2 to the front and back of the module 1 5 times the design load is applied to the module during UL testing 2 4...

Page 12: ...module overlap min 8 mm 8 mm 3 mm 3 mm 256 mm 75 mm 745 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 745 mm 256 mm 75 mm 75 mm 75 mm 75 mm Array Installation section Landscape...

Page 13: ...g cautions Be aware of the necessary grounding requirements prior to installation Your local authorities can help you further Install arrestors surge absorbers or any other appropriate lightning prote...

Page 14: ...r Cables drooping from the terminal box are hazardous and must be avoided Cables should be secured so they are not exposed to direct sunlight such as behind the module The sum of Voc of modules in ser...

Page 15: ...ny other hard materials use only soft cloths or sponges for removing dirt from the SF modules surface When replacement parts are required be sure the installer servicer uses parts specified by the man...

Page 16: ...iafilmplatz 8 82031 Gr nwald bei M nchen Germany Tel 49 89 92 86 142 0 Italy Solar Frontier Europe GmbH Sede Secondaria per l Italia Via Domenico Cotugno 49 A scala B 70124 Bari Italy Tel 39 080 90 21...

Reviews: