6.  Mechanical Installation

6.1  Mechanical Installation Cautions

 • Observe all applicable health and safety regulations when installing SF modules.

 • A safe distance should be cordoned off around the installation area.

 • Fall protection equipment must be used.

 • Installation in windy or wet conditions may require additional precaution. Please follow your local safety regulation.

 • Keep the junction box and the module connector away from any liquids until connectors are mated. 

Failure to do this may cause faulty wiring.

 • Keep SF modules out of reach of children.

6.2  Site Location

 • Ensure that the maximum wind and snow loads in local conditions do not exceed the SF module maximum load ratings.

 • Avoid to install SF modules in areas where they are exposed to oil vapor and /or corrosive gas.

 • Avoid accumulation of grit or dust on the SF modules as it may influence the output yield.

 • Do not expose SF modules to sulphurous atmospheres.

 • Do not install SF modules in locations where flammable gases accumulate or flow as there is a risk of sparks from  

SF modules.

 • Do not install SF modules near fire.

 • Avoid installing SF modules in locations where they may be covered by permanent shadows. This may adversely affect their  

performance.

 • Do not install SF modules in locations where temperatures exceed the temperature range indicated in the module’s  

technical specifications.

6.3  Module Handling Instructions

 • Do not disassemble or modify SF modules. This may result in an electric shock, fire or other accidents. Solar Frontier cannot be held 

responsible for any loss or damage caused by unauthorized disassembling, modification or misuse of SF modules.

 • Do not drill additional mounting holes into the aluminum frame. Only pre-drilled holes should be used.

 • Avoid placing any stress onto the SF modules, cables or connectors.  

(Minimum bending radius of 39 mm for module cables is recommended)

 • Do not stand or step on SF modules. This may result in damage to the module and/ or bodily harm by falling.

 • Do not drop SF modules or drop objects onto them. Both sides of the module (the glass surface and the back sheet) are fragile.

 • Do not strike the terminal box or pull the cables. The terminal box can crack and break, while the output cable may unplug and 

cause electricity leakage or an electric shock.

 • Do not scratch the backsheet or cables of the SF modules. Rubbing or scratching may result in an electric shock, electric leakage or 

an accident.

 • Do not scratch the insulation coating of the frame (except for the grounding connection). This may weaken the strength of the 

frame or cause corrosion.

 • Do not cover the water drain holes of the frame. Doing so may cause frost damage.

 • Do not use glue when closing the cover of the junction box. Similarly, do not use a sealant to bond the junction box lid to its base.

Summary of Contents for SF140-S

Page 1: ...Solar Frontier Europe GmbH Data Sheet and Installation and Maintenance Manual SF140 S SF145 S SF150 S SF155 S SF160 S SF165 S SF170 S ENGLISH...

Page 2: ...2...

Page 3: ...id from August 2013 It replaces all previous changes made to this document Content 1 About this Manual 4 2 General Information 4 3 Technical Data 4 3 1 Electrical Characteristics 4 3 2 Module Performa...

Page 4: ...SF155 S SF160 S SF165 S SF170 S Nominal power Pmax 140 W 145 W 150 W 155 W 160 W 165 W 170 W Power tolerance 5 W 0 W Open circuit voltage Voc 107 0 V 107 0 V 108 0 V 109 0 V 110 0 V 110 0 V 112 0 V S...

Page 5: ...hould not exceed 7 A under any circumstances UL Modules installed in parallel will be provided with the listed maximum series fuse as specified 3 5 Mechanical Data Dimensions L x W x H 1 257 x 977 x 3...

Page 6: ...5 31 1 225 31 1 225 30 12 13 5 35 35 30 372 5 372 5 454 5 454 5 566 5 598 5 5 934 2 21 5 21 5 548 5 120 35 0 5 977 2 90 444 28 2 568 5 5 Mounting holes 2 x Grounding 2 x 4 4 x 8 5 4 x 6 6 Mounting hol...

Page 7: ...circuit voltage must never exceed the maximum system voltage including in low temperature conditions Leakage currents could create a shock hazard or fire Do not disconnect operational modules or elect...

Page 8: ...temperature range indicated in the module s technical specifications 6 3 Module Handling Instructions Do not disassemble or modify SF modules This may result in an electric shock fire or other accide...

Page 9: ...oduction Modules can be installed horizontally landscape or vertically portrait Maintain a space between SF modules and the roof This will allow air to circulate cooling the module and allowing conden...

Page 10: ...0 Pa 50 lbs ft2 to the front and back of the module UL 1 600 Pa 33 4 lbs ft2 to the front and back of the module 1 5 times the design load is applied to the module during UL testing 2 400 Pa 50 lbs ft...

Page 11: ...inimum TUV 2 400 Pa 50 lbs ft2 to the front and back of the module UL 1 600 Pa 33 4 lbs ft2 to the front and back of the module 1 5 times the design load is applied to the module during UL testing 2 4...

Page 12: ...module overlap min 8 mm 8 mm 3 mm 3 mm 256 mm 75 mm 745 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 75 mm 745 mm 256 mm 75 mm 75 mm 75 mm 75 mm Array Installation section Landscape...

Page 13: ...g cautions Be aware of the necessary grounding requirements prior to installation Your local authorities can help you further Install arrestors surge absorbers or any other appropriate lightning prote...

Page 14: ...r Cables drooping from the terminal box are hazardous and must be avoided Cables should be secured so they are not exposed to direct sunlight such as behind the module The sum of Voc of modules in ser...

Page 15: ...ny other hard materials use only soft cloths or sponges for removing dirt from the SF modules surface When replacement parts are required be sure the installer servicer uses parts specified by the man...

Page 16: ...iafilmplatz 8 82031 Gr nwald bei M nchen Germany Tel 49 89 92 86 142 0 Italy Solar Frontier Europe GmbH Sede Secondaria per l Italia Via Domenico Cotugno 49 A scala B 70124 Bari Italy Tel 39 080 90 21...

Reviews: