49
December 2020
|
Solar Stik
®
, Inc.
System Setup and Operation Manual for the Solar Stik G-BOSS E Light HPS
PRELIMINARY
d Initiate System Cycling
1
Toggle Generator Control switch(es) to ON position to start generator(s). Once generator has run
for two(2) minutes, AC input should be qualified.
2
When PRO-Verter enters charging mode, rapidly toggle Generator Control switch(es) to AUTO
position to allow charging cycle to complete automatically.
Figure 40. Generator Mode Control Switches and LEDs
Generator Control Switches
ON
– When the Generator Control switch is in the ON position, the AGS system is activated/
enabled. The PRO-Verter will signal the generator to start. Placing the Generator Control Switch
in the ON position “manually” signals the generator to start using the PRO-Verter AGS controls.
The green status LED will be steady ON.
OFF
– When the AGS switch is placed in the OFF position, the LED status indicator will be off
and all AGS functions are disabled. The green status LED will be steady OFF.
AUTO
– When the Generator Control switch is in the AUTO position, the AGS will start and stop
the generator based on programmed values for battery voltage. When the generator is running,
the status LED will be steady ON.
Note:
Move quickly when switching between ON and AUTO; do not hesitate on the OFF
position. Pausing in the OFF position will inadvertently turn off the generator.
The Generator Status LED blinking pattern indicates the current state of the generators(s). The
graphic below the generator control switches is a key to understanding the blinking pattern.
What to watch for as the System is starting