C o m m i s s i o n i n g
Complete installation of all hydraulic and electrical components is a precondition for
commissioning.
5.1
Leak testing and filling the system
Check all system components, including all pre-fabricated elements and stations, to ensure
they are leak-tight; seal any detected leaks accordingly. When doing this adapt the test
pressure and test duration to match the respective piping system and the respective
operating pressure.
Fill the drinking water side with clean drinking water as per DIN 1988 only; bleed the air from
the system by gradually increasing the pressure.
Note:
Cavitation may develop as a result of excessive flow speeds; this may damage the flow
sensor.
Only fill the heating system, including the primary side of the fresh water system, with filtered,
treated water as per VDI 2035; bleed the system completely.
5.2
First start-up
Please observe the corresponding instructions for the control unit.
Task
Procedure
OK
Preparation and
inspection
Visual inspection of the installation.
Are all of the sensors installed and connected at the
correct location?
Are all outputs connected?
Switch on the
control unit
Supply power to the control unit
Set up the control
unit
Please observe the instructions for the control unit.
Set the fresh water temperature (hot water temperature).
Adjust the circulation (optional).
____
_____
Test outputs
Activate all of the outputs individually in sequence and check to
make sure the pumps switch correctly.
Check functionality
Check the functionality of the hot water supply.
Check the functionality of the circulation (optional).