50
UPS for 208 Vac Grid, B120US Installation Guide, doc. rel. 3.0
To select an address field on the screen, tap the field with your finger. Depending on
the particular model of screen on your system, dragging your finger lightly across
the field from right to left may yield best results.
4.
When you have completed entering all of the addresses, select
Confirm
.
The addresses you entered are saved to the UPS system controller.
3.4.
Testing
Perform the following system functionality tests on the UPS unit.
This section explains how to perform the following tests on the UPS system:
1.
Self loading/PQ mode test
2.
Under load test
3.
Battery mode blackout test
4.
ATS test
5.
ECO Mode test
6.
Check IP Communication with Controller test
The unit offers a self-loading feature that removes the need for load banks or
rewiring of the system.
3.4.1.
Test: Self-loading/PQ mode
This feature is available to do away with standard load bank requirements.
The unit can be configured to simulate resistive, capacitive and inductive test loads.
In order to minimize site disturbance self-loading should be performed with the output CB in the
off position.
To put the system in PQ Mode: