UPS for 400 Vac Grid, Installation Guide, doc. rel. 3.0
23
3.3.
Installation Procedure
After completing each step in the following installation, return to the Installation Checklist
(Section 3.2) and place a checkmark or measurement next to the corresponding item.
The UPS can come in various configuration capacities.
The installation instructions in this guide cover up to the maximum model
configuration capacity.
3.3.1.
Visual Inspection
Perform the inspection described here immediately after unpacking the UPS.
To perform the visual inspection procedure:
1.
Inspect the UPS from all sides and ensure that there is no visible damage to any portion
of the cabinet, the module housings or other coverings.
2.
Verify that the number of modules delivered is as ordered, and that a system controller
module and static switch module were delivered.
3.
Verify that the LCD display screen is undamaged.
The product you received will include a product inventory list. Confirm contents
included in the UPS crate matches the included product inventory list.
3.3.2.
Site Preparation
–
Physical
Perform the following procedures before connecting any external cables to the UPS.
To perform the required procedure:
1.
Ensure that the ambient temperature in the immediate vicinity of the UPS
complies with
system requirements:
Minimum/maximum operating temperatures:
–
10 °C / +40 °C (+14°F / +104 °F).