6 Commissioning
Follow these steps to start up the inverter:
1. Switch ON the DC isolation switch on the lower part of the inverter (see
).
2. Switch on the external switch of the AC feed line connecting the inverter to the grid.
3. Observe the status of LED indicators on the inverter according to the table escribed in
When the LED ndicators indicate a successful grid connection, the inverter is connected and
ready for operation.
Powering OFF the inverter
To take the inverter out of operation, carry out the following steps:
1. Switch off the circuit breaker at AC terminal.
2. Switch OFF the DC isolation switch on the lower part of the inverter (see
10 min
DANGER!
Fatal electric shock hazard!
Components within the inverter are charged with a high voltage
■
Life threatening hazard due to high voltage in the inverter! Disconnect the
voltage from the inverter. Wait 10 minutes before opening the inverter.